Bisha Mining process plant lime Storage

Scope of Work

Client :

Bisha Mining Share Company

Location : Eritera

Schedule: (2022-2023) 

Service Type:

Mining & Construction Services

Scope of Work – Bisha Mining Process Plant Lime Storage Project
  1. Unloading and Handling of Materials On-Site (De-stuffing)

    • Safe offloading of project materials, including lime storage components, structural steel, HDPE pipes, and mechanical equipment.
    • Inspection and verification of received materials against packing lists and specifications.
    • Sorting, temporary storage, and protection of materials to prevent damage and contamination.
    • Coordination with logistics and site supervisors to ensure timely delivery and movement of materials.
  2. Erection of Structural Steel Buildings

    • Assembly and installation of prefabricated steel structures for the lime storage facility.
    • Alignment, bolting, and welding of structural members in accordance with engineering specifications.
    • Application of corrosion protection coatings where required.
    • Quality control inspections to ensure compliance with safety and industry standards.
  3. Erection of Storage Tanks

    • Assembly and installation of lime storage tanks, including base preparation and structural supports.
    • Alignment, bolting, and welding of tank components to ensure structural integrity.
    • Leak testing and pressure testing to verify tank performance.
    • Application of protective coatings to prevent corrosion and contamination.
  4. Fabrication and On-Site HDPE Pole Welding

    • Cutting, shaping, and welding of HDPE pipes and fittings to support lime processing operations.
    • Installation of HDPE pipelines for slurry or chemical transport within the plant.
    • Pressure testing and integrity checks to ensure leak-proof connections.
    • Compliance with industry standards for HDPE welding and jointing techniques.
  5. Installation of Mechanical Pumps

    • Positioning and alignment of mechanical pumps used in lime slurry and fluid transfer.
    • Piping connection, bolting, and integration with plant processing systems.
    • Testing and commissioning of pumps to ensure optimal performance.
    • Routine maintenance and troubleshooting of installed pumps.
  6. Erection of Scaffolding Systems

    • Supply, assembly, and installation of scaffolding for structural works, tank erection, and maintenance access.
    • Compliance with OSHA and site-specific safety standards for working at heights.
    • Load testing and certification of scaffolding before use.
    • Dismantling and removal of scaffolding upon project completion.
  7. Rigging and Lifting Operations On-Site

    • Planning and execution of rigging activities for heavy equipment, tanks, and structural components.
    • Use of cranes, chain blocks, and hoisting equipment for safe lifting.
    • Load balancing and securing to prevent hazards during lifting operations.
    • Coordination with certified riggers to ensure safety and efficiency.
  8. On-Site Maintenance and Repair Works

    • Routine and preventive maintenance of installed structures, pipelines, and mechanical systems.
    • Troubleshooting and repair of pumps, HDPE pipelines, and structural components.
    • Emergency maintenance services to minimize downtime.
    • Compliance with plant maintenance schedules and reporting requirements.

The Bisha Mining Process Plant Lime Storage Project ensures:

  1. Efficient Lime Handling – Secure storage and smooth transport of lime for mining operations.
  2. Structural Stability – Safe and durable erection of buildings and tanks.
  3. Reliable Pumping & Piping – Leak-proof and corrosion-resistant fluid transfer systems.
  4. Safe Material Handling – Proper unloading, rigging, and lifting of equipment.
  5. Workplace Safety – Compliance with health and safety standards.
  6. Operational Reliability – Preventive maintenance to minimize downtime.
  7. Environmental Compliance – Safe lime storage and reduced environmental impact.