Anti-Scalant Pipes Installation Project

Client :

Bisha Mining Share Company

Location : Eritera

Schedule: 2024

Service Type:

Mining & Construction Services

Project Detail

The Anti-Scalant Pipes Installation Project involves the design, fabrication, and installation of high-quality anti-scalant pipes and dosing systems. The system delivers precise chemical dosing to prevent scaling in reverse osmosis (RO), desalination, and water treatment plants.

This project is part of Skargi Africa’s ongoing commitment to deliver innovative water management solutions that improve operational efficiency, extend equipment lifespan, and ensure compliance with environmental standards.


Scope of Work

a. Design and Engineering
  • Conduct site assessments to determine flow rates, chemical dosing requirements, and pipeline routing.

  • Design the anti-scalant dosing network, including suction lines, discharge lines, and dosing points.

  • Select pipe materials resistant to corrosion, chemical reactions, and high pressure.

  • Prepare detailed engineering drawings, layout plans, and installation schematics.

b. Procurement and Fabrication
  • Supply anti-scalant pipes, fittings, valves, and accessories as per project specifications.

  • Fabricate custom piping components to meet design and operational needs.

  • Perform pre-installation inspection and quality checks on all materials.

c. Installation and Commissioning
  • Execute site preparation, pipeline alignment, and support structure installation.

  • Connect dosing pumps, tanks, and control panels to the pipeline network.

  • Conduct pressure and leak testing of all joints and fittings.

  • Calibrate dosing systems and perform trial runs to verify performance.

  • Commission the Anti-Scalant Pipes Installation Project for full operational use.

d. Quality Assurance and HSE Compliance
  • Implement Skargi Africa’s Health, Safety, and Environment (HSE) standards throughout the project.

  • Ensure safe handling and installation of chemical dosing systems.

  • Maintain inspection reports, test results, and quality documentation.

e. Training and Handover
  • Provide training for plant operators and maintenance staff on system operation and troubleshooting.

  • Deliver as-built drawings, calibration certificates, and user manuals.

  • Officially hand over the completed Anti-Scalant Pipes Installation Project to the client.


Project Objectives

  • To design and install an efficient anti-scalant piping system for optimal chemical dosing.

  • To prevent scale formation and fouling in industrial water systems.

  • To ensure system reliability and operational safety.

  • To extend the lifespan of RO membranes and process equipment.

  • To comply with all engineering and environmental standards.


Expected Outcomes

Upon completion, the Anti-Scalant Pipes Installation Project will deliver:

  • Improved plant performance through controlled anti-scalant dosing.

  • Reduced downtime and maintenance costs.

  • Enhanced water treatment efficiency and product quality.

  • Sustainable and safe operation in compliance with international standards.

This project underscores Skargi Africa Engineering & Construction Ltd.’s leadership in delivering specialized mechanical and process infrastructure that meets the evolving needs of modern industries.