Bisha Mining process plant water line

Scope of Work

Client :

Bisha Mining Share Company

Location : Eritera

Schedule: (2022-2023) 

Service Type:

Mining & Construction Services

Scope of Work – Bisha Mining Process Plant Water Line Project
  1. Welding and Fabrication of HDPE Pole Pipe

    • Cutting, aligning, and welding of HDPE pipes for water distribution.
    • Butt fusion, electrofusion, and extrusion welding techniques to ensure strong, leak-proof joints.
    • On-site fabrication and customization to fit pipeline layouts.
    • Pressure testing to verify structural integrity and compliance with industry standards.
  2. Welding of Steel Pipe

    • Preparation, cutting, and welding of steel pipes for high-pressure water transportation.
    • Use of MIG, TIG, and arc welding techniques to ensure durable and corrosion-resistant joints.
    • Pipe alignment, inspection, and quality control to meet engineering specifications.
    • Application of protective coatings to enhance longevity and resistance to harsh conditions.
  3. Pressure Testing and Installation of Pumps

    • Conducting hydrostatic and pneumatic pressure tests to ensure pipes and fittings are leak-proof.
    • Installation and alignment of water pumps for efficient fluid transfer.
    • Connection of pumps to pipelines with secure fittings and valves.
    • Testing and commissioning to verify operational efficiency.
  4. Plant Shutdown and Maintenance

    • Scheduled shutdown procedures for the maintenance and upgrading of water lines.
    • Inspection, repair, and replacement of worn-out pipes, valves, and pump components.
    • Cleaning and flushing of pipelines to remove blockages and maintain water flow efficiency.
    • Coordination with plant operators to minimize downtime and ensure safety compliance.
  5. Rigging and Lifting of Pipes and Steel Structures

    • Safe lifting and positioning of large-diameter pipes and structural components.
    • Use of certified rigging equipment, slings, and lifting techniques to prevent damage.
    • Coordination with crane operators and riggers to ensure precision and safety.
    • Compliance with weight limits and load distribution requirements.
  6. Crane Operations On-Site

    • Operation of mobile and tower cranes for lifting and placing heavy materials.
    • Adherence to safety protocols for crane maneuvering in restricted areas.
    • Regular inspections and maintenance of lifting equipment to ensure reliability.
    • Coordination with site engineers for safe and efficient material handling.

The Bisha Mining Process Plant Water Line Project ensures:

  1. Reliable Water Supply – Secure and efficient water transportation for mining operations.
  2. Strong and Leak-Proof Pipelines – High-quality HDPE and steel pipe welding to prevent leaks and failures.
  3. Efficient Pump Performance – Proper installation and testing of pumps for optimal water flow.
  4. Minimal Downtime – Planned shutdowns and maintenance to ensure continuous operations.
  5. Safe Material Handling – Rigging and lifting of pipes and structures with strict safety measures.
  6. Precision Crane Operations – Safe and efficient lifting of heavy components to enhance project efficiency.
  7. Regulatory Compliance – Adherence to industry standards and environmental safety protocols.