Bisha Mining process plant water line
Scope of Work
Client :
Bisha Mining Share Company
Location : Eritera
Schedule: (2022-2023)
Service Type:
Mining & Construction Services
Scope of Work – Bisha Mining Process Plant Water Line Project
Welding and Fabrication of HDPE Pole Pipe
- Cutting, aligning, and welding of HDPE pipes for water distribution.
- Butt fusion, electrofusion, and extrusion welding techniques to ensure strong, leak-proof joints.
- On-site fabrication and customization to fit pipeline layouts.
- Pressure testing to verify structural integrity and compliance with industry standards.
Welding of Steel Pipe
- Preparation, cutting, and welding of steel pipes for high-pressure water transportation.
- Use of MIG, TIG, and arc welding techniques to ensure durable and corrosion-resistant joints.
- Pipe alignment, inspection, and quality control to meet engineering specifications.
- Application of protective coatings to enhance longevity and resistance to harsh conditions.
Pressure Testing and Installation of Pumps
- Conducting hydrostatic and pneumatic pressure tests to ensure pipes and fittings are leak-proof.
- Installation and alignment of water pumps for efficient fluid transfer.
- Connection of pumps to pipelines with secure fittings and valves.
- Testing and commissioning to verify operational efficiency.
Plant Shutdown and Maintenance
- Scheduled shutdown procedures for the maintenance and upgrading of water lines.
- Inspection, repair, and replacement of worn-out pipes, valves, and pump components.
- Cleaning and flushing of pipelines to remove blockages and maintain water flow efficiency.
- Coordination with plant operators to minimize downtime and ensure safety compliance.
Rigging and Lifting of Pipes and Steel Structures
- Safe lifting and positioning of large-diameter pipes and structural components.
- Use of certified rigging equipment, slings, and lifting techniques to prevent damage.
- Coordination with crane operators and riggers to ensure precision and safety.
- Compliance with weight limits and load distribution requirements.
Crane Operations On-Site
- Operation of mobile and tower cranes for lifting and placing heavy materials.
- Adherence to safety protocols for crane maneuvering in restricted areas.
- Regular inspections and maintenance of lifting equipment to ensure reliability.
- Coordination with site engineers for safe and efficient material handling.
- PROGRESS PICTURES & VIDEOS OF PROJECT
The Bisha Mining Process Plant Water Line Project ensures:
- Reliable Water Supply – Secure and efficient water transportation for mining operations.
- Strong and Leak-Proof Pipelines – High-quality HDPE and steel pipe welding to prevent leaks and failures.
- Efficient Pump Performance – Proper installation and testing of pumps for optimal water flow.
- Minimal Downtime – Planned shutdowns and maintenance to ensure continuous operations.
- Safe Material Handling – Rigging and lifting of pipes and structures with strict safety measures.
- Precision Crane Operations – Safe and efficient lifting of heavy components to enhance project efficiency.